Singareni proposals at another 350 MW Floating Solar Plant at Lower Manor Dam

CMD N. Sridhar reviewed on 350 MW floating solar plant

C&MD is also planning to setup a 350 MW floating solar plant to be built by Singareni on the waters of the Lower Maneru Dam. Discussed in detail. The DPR said that proposals for the construction of the plant have been submitted to the government. Officials explained that the agency was also hired to prepare a report on the possibilities and future of the plant construction prior to design. The agency will visit the dam next week to collect water level, inflow data, sedimentation, etc. information related to the Lower Manor Dam for the last 20 years and hand it over to the Solar Energy Corporation of India..

After examining the feasibility report, the D.P.R. C&MD said it would be designed and approved by the government. Revealed by Shri N. Sridhar. He directed the Director E&M not to take any special initiative on the solar plant proposal on the Maneru Dam. He later reviewed the progress of the Singareni Thermal Power Plant. The thermal power plant was directed to contribute to the progress of the state by providing quality electricity with good PLF as in the past.

Singareni: 300 MW of solar power to be provided by next October: CMD N Sridhar
Singareni CMD N. Sridhar review on 3rd phase construction and 350 MW Floating Solar Plant Proposal on Lower Manor Dam.

Singareni has set a time-bound target of completing the construction of nine solar power plants in three phases across the company by October this year and bringing the full 300 MW of solar power to the grid. Directed by Mr.N. Sridhar CMD

He conducted a review with Director E&M Shri D. Satyanarayana Rao along with representatives of Singareni Solar, Thermal Power Officers, Solar Plant Construction Agencies BHEL, Adani and Novas Green at Singareni Bhavan, Hyderabad today. The first phase of construction of 129 MW solar power plants in Singareni has been completed, 39 in Illandu, 30 in Manuguru, 30 in Ramagundam-3 and 10 MW in Singareni Thermal Power Station are generating electricity.

The second of the two plants under construction in Mandamarri with a capacity of 15 MW will be connected to the grid on Thursday (April 8) and the 28 MW 1st plant under construction in the same area will be commissioned within another week. He also directed to start the 10 MW plant at Bhupapalli by the end of this month and to complete the 37 MW plant under construction at Kottagudem by May 15. With this, the second phase of 90 MW plants will be completed. Construction agency Adani Group has been directed to complete the second phase of construction in a timely manner.

He also reviewed the progress of the 81 MW solar plants to be built in the third phase. Construction agency Novas Green reviewed with representatives on the progress of work on a 15-megawatt solar plant floating on water in the water reservoir at the Singareni Thermal Power Plant. The plant was ordered to be completed by the end of October and connected to electricity.

As well as R.G.OC-3 dumps on the 22 MW plant, which will be located. It will be built at Dorley OC Adani and Novas Green, the construction companies, have directed the government to complete the 10 MW plant on dumps, the 23 MW plant at Kottagudem and the 11 MW plant at Chennur by September and October, and to complete a total of 300 MW by October under all circumstances.Maneru Dam.

In this program G.M. Solar Sri Suryanarayana Raju, G.M. Workshops Shree Nageswararao, Director (E&M) Shri Vishwanadharaju, Solar Consultant Shri Muralitharan and others participated.